Former OPG Thunder Bay Generating Station Decommissioning

 

SYNOPSIS

The former coal fired power generation station had three boilers over 91.4 m (300 ft), three turbines, three precipitators over 60.96 m (200 ft), a 198 m (650 ft) concrete stack, a water inlet and outlet, and associated outbuildings.  Work started onsite in April 2021 with a large asbestos abatement of Boiler# 1 and prepping the stack for felling and removal of the turbine hall to the north of the boilers.

 

The stack was felled using explosives in September 2021, the precipitators were detached from the boilers and dropped using explosives in December, and finally the top hung boilers were toppled using explosives in June 2022. A large piece of the project is the sorting, categorizing, preparing, and shipping offsite the ferrous and non-ferrous scrap metals.

 

Large second member shears and torch men have been working diligently to move the material offsite via truck and rail. The project included abatement of the boiler refractory, demolition of the power generating station, processing and disposal of all construction and demolition waste, and recycing all scrap steel.

 

BIOGRAPHY

Jason has 22 years of experience in the demolition industry. His experience includes director of projects, senior project manager, supervisor, operator and foreman.

 

Having worked with some of Canada’s largest demolition companies, Jason has vast experience with creating demolition programmes, emergency response management, demolition of unstable structures, hazardous material abatement and creation and implementation of site safety and site access protocols.

 

The list also includes hazardous materials removal and disposal programmes, environmental management plans, services installation and re-route work, onsite concrete recycling and investment recovery.

 

He has worked extensively with owners, architects, consultants, suppliers and contractors to ensure project are delivered on schedule and on budget.

 

 

 

 

 

 

 

 

 

MEDIA PARTNERS

HEADLINE SPONSOR

GOLD SPONSORS

BRONZE SPONSORS

PRE-AWARDS DRINKS

EVALUATION SPONSOR

SILVER SPONSORS

TABLE WINE SPONSOR

WATER SPONSOR

BREAKFAST SPONSOR

WELCOME DRINKS

Created and organised by

in partnership with

in cooperation with